Good morning, Marcus

Ridgeline Build Co. · 4 active projects · next payroll Friday

Bridge this week's crew costs before the River Oaks draw clears
$28,400 in labor and materials due Friday · River Oaks draw of $62,000 arrives May 15 · 8 days out
Available
$28,400.00
Active projects
4
$916,500 total contract
Draws pending
$109,200
2 submitted, awaiting payment
Open change orders
$41,200
3 COs · 2 signed
Sub invoices due
$31,800
Due within 7 days
Active jobs
ProjectContract valuePhaseProgressStatus
River Oaks Residence
D. Callahan
$247,500Framing
38%
On Track
Elk Ridge Addition
M. & T. Sousa
$89,000Rough-in
62%
On Track
Cedar Ridge Full Reno
Priya N.
$168,000Drywall
71%
CO Pending
Foxhollow New Build
J. Aaronson
$412,000Foundation
14%
On Track
Upcoming draws
River Oaks Residence
Submitted Apr 28 · Expected May 15
$62,000.00
Cedar Ridge Full Reno
Submitted May 2 · Expected May 18
$47,200.00